i just nak share yang my final exam akan tiba.. OH MY GOD!!! so sekarang ni i tengah sibuk mengulang kaji la kan.. * kononnye la.. study week diberi seminggu, tapi lagi 3 hari before exam i baru nak bukak buku. tapi agak oke la jugak kan lagi 3 hari.. ade yang i tengok kat facebook, malam exam baru bukak.. OMG... tapi mungking mereka pandai dan dah study awal2 kan..bukan boleh percaya sgt cakap mereka ni.. nnti tup2.. dorg dpt higher pointer.. kan kan kan.. so first skali yang i study adalah cost palnning and control. kami dapat soalan bocor tau.. tpi kalau x dapat jawab jugak x tau ler den nak cakap kot mano laie... hehe..
xoxo
ni ha yang i bace untuk soalan 1 :
Clients’
requirements for an accurate forecast of the overall cost is due to:-
o
resources
such as land and materials becoming scarce and expensive.
o
modern
buildings becoming more complex,
o
fluctuation
in labour and material cost etc.
what is cost
planning
Ø
Cost
plan is prepared by finding a cost analysis of a similar project to the one
under consideration, and by studying how the cost was allocated in the old
project, in order to prepare an estimate for the new scheme.
Ø
The
cost information cannot be used directly from the cost analysis, and some
degree of modification will have to be made.
Ø
These
modifications are usually for differences in
v
price
level
v
Quantity
v
Finishes
and standards
What is cost
control
v
Techniques
for “protecting” the cost plan.
v
Generic
term embracing all methods of controlling the cost of a building throughout its
various stages from inception to completion.
v
Process
of cost checking required the estimated cost of each element to be checked
against the target set set in the cost plan.
There are 3
basic principles of cost control :
·
There
must be a frame of reference or a set of condition, which must be adhered to.
·
There
must be a method of checking or a feedback system
·
There
must be a means of remedial action.






i.
If
the cost of the element design is greater than a realistic cost target, the
element design should be changed so that it is within the cost target.
ii.
If
the cost check of the element design shows that the cost target is unrealistic,
cost target should be adjusted throughout the cost plan, thereby releasing
funds from other elements.